You need to update the Northwind2U program to reflect the change of resource, and then deliver the requested r

You need to update the Northwind2U program to reflect the change of resource, and then deliver the requested report. What should you do before you begin the update?

PrepAway - Latest Free Exam Questions & Answers

A.
Overwrite the default baseline for reporting purposes.

B.
Set a baseline that has not previously been used for reporting purposes.

C.
Create a copy of the project on the server for comparison to the updated project.

D.
Save a copy of the project as a Microsoft Office Project Professional 2007 project file.