You need to assist Chris Ashton in resolving her issue

You need to assist Chris Ashton in resolving her issue. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Synchronize the project with actuals.

B.
Confirm a status date exists for the project.

C.
Add the Actual Work column to the Gantt chart.

D.
Add the Baseline Work column to the Gantt chart.