In Microsoft Office Project Web Access, what should you do?

You need to create a view that will meet David Pelton’s requirement for performance reporting. In Microsoft Office Project Web Access, what should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Add the CPI and SPI fields to the Project Center Tracking view.

B.
Add the CVP and SVP fields to the Project Center Tracking view.

C.
Using formulas and visual indicators, create project fields named CPI Indicator and SPI Indicator. Add both fields to the Project Center Tracking view.

D.
Using formulas and visual indicators, create task fields named CPI Indicator and SPI Indicator.
Add both fields to the Project Details Task Tracking view.