PrepAway - Latest Free Exam Questions & Answers

You need to respond to managements schedule request for the Package Infrastructure project

You need to respond to managements schedule request for the Package Infrastructure project. You have identified affected tasks and available resources. What should you do next?

PrepAway - Latest Free Exam Questions & Answers

A.
Assign resources to effort driven tasks.

B.
Assign resources to fixed duration tasks at 80% units.

C.
Assign resources to fixed duration tasks at 10% units.

D.
Assign resources to fixed duration tasks at 20% units.


Leave a Reply