PrepAway - Latest Free Exam Questions & Answers

You need to bring the task back on track by using new contractors

One of Trey Research’s critical tasks is delayed. You need to bring the task back on track by using new contractors. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Add the new contractors to a shared resource pool, and assign them to the task.

B.
Add the new contractors to the Enterprise Resource Pool, and assign them to the task.

C.
Add the new contractors to the Resource Sheet of the project, and assign them to the task.

D.
Enter the new contractors in the Resource Name column of the project plan, and assign them to the task.


Leave a Reply