You need to create a view that will indicate whether project managers are fulfilling the requirements for updating their projects. Which view should you create?

PrepAway - Latest Free Exam Questions & Answers

A.
A view that displays a status date greater than today’s date.

B.
A view that displays unfinished work prior to the status date.

C.
A view that displays all unstarted tasks that start after the status date.

D.
A Resource Usage view that displays only actual work prior to the status date.