You need to implement the new scope management policy

You have added tasks to your project plan. You need to implement the new scope management policy. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Select all tasks and rebaseline the project plan.

B.
Select all tasks and save an interim plan for the entire project.

C.
Select the new tasks and add these tasks and their predecessor tasks to the existing baseline.

D.
Select the new tasks and add these tasks and their successor tasks to the existing baseline.