You need to address management’s requirement for viewing their key initiatives

You need to address management’s requirement for viewing their key initiatives. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a Project Center view that displays the status indicators, filters by initiative name, and sorts by ROI.

B.
Create a Project Center view that displays the status indicators, filters by ROI, and sorts by initiative name.

C.
Create a Data Analysis view that displays cost data across all projects. Add the initiative name and ROI as filter values.

D.
Create a Data Analysis view that displays cost data across all projects sorted by ROI. Add the initiative name as a filter value.