You need to evaluate resource availability for the next six months

You’ve recently approved a project that is scheduled to begin in two months. You need to evaluate resource availability for the next six months. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Set the value in a custom project status field to Approved.

B.
Publish all assignments for the project plan to Project Server.

C.
Replace all generic resources with proposed enterprise resources.

D.
Replace all generic resources with committed enterprise resources.