You need to evaluate the availability of bike helmet designers for an approved project that will begin in two

You need to evaluate the availability of bike helmet designers for an approved project that will begin in two months. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
In the Resource Center, select Brenda Diaz, Steve Lasker, and Tai Yee. View their availability including their proposed assignments.

B.
In the Resource Center, select Brenda Diaz, Steve Lasker, and Tai Yee. View their availability based only on assigned work that has been committed to project plans.

C.
In Microsoft Office Project Professional 2007, use the Build Team interface to select the generic resource for Bike Helmet Designer. View the resources availability, including any proposed assignments.

D.
In Project Center, use the Build Team interface for the project and select the generic resource for Bike Helmet Designer. View the resources availability based only on assigned work that has been committed to project plans.