You need to provide a report to project sponsors

You need to provide a report to project sponsors. What should you do first?

PrepAway - Latest Free Exam Questions & Answers

A.
Request a status report from each sponsor.

B.
Submit an unrequested status report to each sponsor.

C.
Create an enterprise project field named Sponsor and associate it with each project. Create a Project Center view to filter on that field.

D.
Create an enterprise task field named Sponsor and associate the field with each task. Create a Project Details view to filter on that field.