PrepAway - Latest Free Exam Questions & Answers

You need to provide David Pelton with the requested information regarding project schedule

You need to provide David Pelton with the requested information regarding project schedule.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a Project Center view to display the Finish Variance and Finish fields.

B.
Create a Project Center view to display the Baseline Finish and Actual Finish fields.

C.
Create a Project Details view to display the Baseline Finish field.

D.
Create a Project Details view to display the Finish Variance and Finish fields.