You need to generate an earned value report that fulfills management’s requirements. What should you do?
A.
Configure a Project Detail view with earned value fields.
B.
Configure a Project Center view with earned value fields.
C.
In Microsoft Office Project Professional 2007, create a visual report.
D.
In Microsoft Office Project Professional 2007, display the Earned Value table.