You need to create the resources in your company’s resource pool so that the new staffing model will be

You need to create the resources in your company’s resource pool so that the new staffing model will be implemented during the initial stages of a project. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a cost-type resource named generic.

B.
Create a work-type resource named generic.

C.
Create a work-type resource for each qualification.

D.
Create a generic work-type resource for each qualification.