you need to update the task so that dependent tasks will be rescheduled

An activity plan that is published to Microsoft Office Project Server 2007 has a task scheduled to take 5 more days. The resource assigned to the task tells you that the task requires 2 more days, instead of 5 more days. In Microsoft Office Project Web Access, you need to update the task so that dependent tasks will be rescheduled. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Delete the task in the activity plan, create a new task with 2 days duration, and assign the resource to the new task.

B.
Edit the task details to reduce the duration by 3 days.

C.
Accept the resource timesheet with actual time worked by the resource, but reject the task update.

D.
Submit a surrogate timesheet for the resource with the difference in work reported as administrative non-working time.