PrepAway - Latest Free Exam Questions & Answers

You need to commit the named resources in your plan as replacements for the generic resources

In a project that is published to Microsoft Office Project Server 2007, each task has both a generic resource and a matching proposed named resource assigned. You receive approval to use these named resources for the proposed assignments. You need to commit the named resources in your plan as replacements for the generic resources. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Change the booking type of the named resources from Proposed to Committed, remove the generic resources, and then publish the plan.

B.
Change the booking type of the generic resources from Proposed to Committed, change the booking type of the named resources from Proposed to Committed, and then publish the plan.

C.
Change the booking type of the generic resources from Proposed to Committed, replace them with named resources, and then publish the plan.

D.
Add the named resources to your plan, using a booking type of Committed.


Leave a Reply