PrepAway - Latest Free Exam Questions & Answers

On what should you base the resource utilization?

You create a project plan with a resource plan in Microsoft Office Project Server 2007. You can estimate work of individual tasks in the current phase, but you cannot estimate work of individual tasks in the next phase. You do not want to create dummy tasks in the project plan to manage resource utilization. You need to calculate the resource utilization of your project resources based on work in the current phase and the next phase. On what should you base the resource utilization?

PrepAway - Latest Free Exam Questions & Answers

A.
The project plan

B.
The resource plan

C.
The project plan for the current phase and the resource plan for the next phase

D.
The hours in the project plan and the full-time equivalents in the resource plan


Leave a Reply