Your project is published to Microsoft Office Project Server 2007. You want to receive a status report from your team once a week. You want the reports of all the individual team members to be combined automatically into a single status report. You need to set up automatic status reporting. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
By e-mail, ask resources to submit an unrequested status report at least once a week.

B.
In Microsoft Office Project Web Access, submit an unrequested status report.

C.
In Microsoft Office Project Web Access, create a new status report request.

D.
In Microsoft Office Project Professional 2007, add a recurring task to remind team members to submit a status report once a week.