In a set of projects that are saved to Microsoft Office Project Server 2007, a custom field is used to indicate project status. You are asked to create a report listing all Active and Completed projects. The report should display graphical indicators to show whether the projects are within budget and schedule. You need to create a view in Microsoft Office Project Web Access so that you can generate this report. What type of view should you create?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Center

B.
Data Analysis

C.
Team Tasks

D.
Resource Assignments