you need to replace the generic resource assignments with named resource assignments that have the required sk

In a plan that is published to Microsoft Office Project Server 2007, you have assigned generic resources to the tasks based on required skills. In Microsoft Office Project Professional 2007, you need to replace the generic resource assignments with named resource assignments that have the required skills. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Use the Resource Substitution Wizard to replace the generic resources with named resources who have the right skills.

B.
Assign the named resources to your project. Then in the Resource Usage view, copy the assignments from the generic resources to the named resources.

C.
Use the Build Team from Enterprise feature to select all named resources whose skills match those of the assigned generic resources. Then add all relevant resources to your project.

D.
Use the Build Team from Enterprise feature to remove generic resources from the project.