You need to move your task to match the deliverable finish date

In Microsoft Office Project Professional 2007, you have a project plan that has a task linked to a deliverable in another project. The Gantt chart shows that the other project deliverable finish date is a week in the future. You need to move your task to match the deliverable finish date. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
In the Dependency pane, select Get Updates.

B.
In the Dependency pane, select Accept Changes from the Server for the appropriate deliverable.

C.
Set a deadline on the task.

D.
Update the Start date of the task.