You need to transfer the resources you used in the resource plan to the project plan

You create a resource plan for a proposal in Microsoft Office Project Web Access. The proposal is approved, and you now need to create a project plan. You need to transfer the resources you used in the resource plan to the project plan. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Set the resource plan options to calculate resource utilization from the project plan.

B.
Set the resource plan options to calculate resource utilization from the resource plan.

C.
Synchronize the resources from the resource plan to the project plan on the Team Builder page.

D.
Assign the resources on the Build Resource Plan Team page.