you need to replace the old resource on all of his remaining scheduled work with the new resource

You manage a project that is published to Microsoft Office Project Server 2007. A resource has quit his job, and a replacement has been hired. In Microsoft Office Project Professional 2007, you need to replace the old resource on all of his remaining scheduled work with the new resource. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
In the Assign Resources dialog box, replace the old resource with the new resource.

B.
Assign the new resource to the project. Then in the Resource Usage view, copy all of the old resources tasks to the new resource.

C.
Break each task to which the old resource is assigned into two: a completed task and a task with remaining work. Then assign the remaining work to the new resource.

D.
Clear the actual work from all the tasks to which the old resource is assigned. Then globally replace the old resource with the new resource.