You need to display any delay of the preceding task without the succeeding task being automatically reschedule

In a project that is published to Microsoft Office Project Server 2007, a task cannot start until a task in another project is completed. You need to display any delay of the preceding task without the succeeding task being automatically rescheduled. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Link the tasks with a finish-to-finish dependency.

B.
Link the tasks with a start-to-finish dependency.

C.
Use a temporary master project plan to link the tasks.

D.
Link the task to a deliverable in the preceding project plan.