you need to request a named resource from the enterprise resource pool for each generic resource

A project that is saved to Microsoft Office Project Server 2007 currently contains generic resources. The next step is to replace the generic resources with named resources who are available to work on your project. From the Build Team from Enterprise screen in Microsoft Office Project Professional 2007, you need to request a named resource from the enterprise resource pool for each generic resource. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Replace each generic resource with an enterprise resource, and then book that resource as Committed.

B.
Replace each generic resource with an enterprise resource, and then book that resource as Proposed.

C.
Replace each generic resource with an enterprise resource, and then use Assign Resources to modify each assignment for this resource by setting the R/D field to Request.

D.
Replace each generic resource with an enterprise resource, use Assign Resources to modify each assignment for this resource by setting the R/D field to Request, and then level all resources to ensure availability.