PrepAway - Latest Free Exam Questions & Answers

You need to identify tasks that have been reassigned

In a project that is published to Microsoft Office Project Server 2007, resources reassign tasks to other resources as necessary. You need to identify tasks that have been reassigned. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Schedule the e-mail reminder service to run every day at 12:00 noon.

B.
Create a task to check when a resource reassigns a task.

C.
Review the Task Updates page.

D.
Set up a rule to approve all task assignments.


Leave a Reply