You need to be able to record time spent on unplanned, non-project activities

Your organization tracks resource utilization using Microsoft Office Project Server 2007. Your project time is captured on the task level. You need to be able to record time spent on unplanned, non-project activities. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a status report request.

B.
Create a new task on your My Tasks page.

C.
Create a new line on your My Timesheets page.

D.
Ask your manager to generate a resource plan.