You need to associate the new issue with the project plan

You manage a project that is published to Microsoft Office Project Server 2007. The deadline for a task that involves printing several documents has passed. In Microsoft Office Project Web Access, you create a new issue. You need to associate the new issue with the project plan.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Link the issue to the documents.

B.
Link the issue to the delayed task.

C.
Link the issue to a risk.

D.
Link the issue to another issue.