You create and save a project schedule in Microsoft Office Project Professional 2007. You need to add some deliverables to your project tasks. However, the Manage Deliverables feature is not available. What should you do?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Publish the project plan with a project workspace site.
B.
Save the project plan as a workspace.
C.
Save the project plan to a project workspace site.
D.
Use the Manage Dependencies on Deliverables feature.