You are tracking a set of projects that are saved to Microsoft Office Project Server 2007. Your organization’s directors have requested a weekly report displaying the progress of all active projects. They want to see cost and work grouped by a custom field for product. They cannot log on to Microsoft Office Project Web Access. In Project Web Access, you need to supply this report. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
On the Status Reports page, submit an unrequested status report to the directors.

B.
On the Project Center page, create a new activity, and associate the custom field for product with it. Then export the grid to a Microsoft Office Excel worksheet.

C.
On the Project Center page, group by product, and then export the grid to a Microsoft Office Excel worksheet.

D.
On the Data Analysis page, create a view that groups cost and work by the custom field for product.