PrepAway - Latest Free Exam Questions & Answers

which Phase of the TOGAF ADM are the Architecture Roadmap and the Implementation and Migration Plan integrated

In which Phase of the TOGAF ADM are the Architecture Roadmap and the Implementation and
Migration Plan integrated with other change activity in the enterprise?

PrepAway - Latest Free Exam Questions & Answers

A.
PhaseA

B.
PhaseD

C.
PhaseE

D.
PhaseF

E.
PhaseG

2 Comments on “which Phase of the TOGAF ADM are the Architecture Roadmap and the Implementation and Migration Plan integrated

  1. js says:

    TOGAF 9.1 book, section 13.4.11 – “The Implementation and Migration Plan must demonstrate the activity necessary to realize the Architecture Roadmap. The Implementation and Migration Plan forms the basis of the migration planning in Phase F.”

    Section 14.1 – “Ensure that the Implementation and Migration Plan is coordinated with the enterprise’s approach to managing and implementing change in the enterprise’s overall change portfolio.”

    The answer is D.