which of the following is the best answer?

Scenario

Acme Widgets Inc.
Please read this scenario prior to answering the question Acme Widgets Inc. manufactures a variety
of small electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, it has
defined a strategic architecture to improve its ability to meet consumer demand and improve its
ability to manage its supply chain. The strategic architecture called for the consolidation of multiple
Enterprise Resource Planning (ERP) applications that have been operating independently in several
of the divisions’ production facilities. The goal is to replace the functionality of the existing
applications with a new ERP product running as a single instance in the company’s primary data
center. Acme has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its
architecture framework, [n addition to the EA program, Acme has a number of management
frameworks in use, including business planning, portfolio/project management, and operations
management. The EA program is sponsored by the CIO. Each division has completed the Architecture
Definition documentation required to tailor and configure the environment to meet its own specific
manufacturing requirements. The enterprise architects have analyzed the key corporate change
attributes and implementation constraints. A consolidated gap analysis has been completed which
has identified the gaps across the Business, Data, Application, and Technology domains. Based on
the results of the gap analysis, the architects have reviewed the functional requirements and
interoperability requirements needed to integrate the new ERP environment into the existing
environment. Based on all of these factors, the architects have assessed the organization’s readiness
to conduct the business transformation and have produced a risk assessment. Because of the risks
posed by the complexity of the current environment, it has been determined that a phased
approach is needed to implement the target architectures. The overall implementation process is
estimated to take several years. Refer to the Acme Widgets Scenario Your role is consultant to the
Lead Architect. The Implementation and Migration Plan v.0.l, the Transition Architectures v1.0, and
the Capability Assessment deliverables are now complete. You have been asked to recommend the
next steps to prepare the final Implementation and Migration Plan. Based on TOGAF 9, which of the
following is the best answer?

PrepAway - Latest Free Exam Questions & Answers

A.
You would apply the Business Value Assessment Technique to prioritize the implementation
projects and project increments. Thus assessment should focus on return on investment and
performance evaluation criteria that can be used to monitor the progress of the architecture
transformation. You would confirm the Transition Architecture phases using an Architecture
Definition Increments Table to list the projects. You would then document the lessons learned and
generate the final plan.

B.
You would conduct a set of Compliance Assessments to ensure that the implementation team is
implementing the architecture according to the contract(s). The Compliance Assessment should also
ensure that the implementation team is using the proper development methodology. It should
include deployment of monitoring tools and ensure that performance targets are being met. If they
are not met, then changes to performance requirements should be identified and updated in the
Implementation and Migration Plan.

C.
You would assess how the plan impacts the other frameworks in use. Minimally, the plan should
be coordinated with the business planning, portfolio/project management and operations
management frameworks. You would then assign a business value to each project, taking into
account available resources and priorities for the projects. Finally, you would generate a time-lined
Implementation and Migration Plan.

D.
You would place the strategic Architecture Definition and Transition Architectures under
configuration control as part of the ongoing evolution cycle. This will ensure that the architecture
remains relevant and responsive to the needs of the enterprise. You would then produce an
Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You
recommend that lessons learned be accepted by the Architecture Board as changes to the
architecture without review.

18 Comments on “which of the following is the best answer?

  1. Sivix says:

    D is wrong my opinion. Changes to architecture cannot be accepted without review.
    C is more TOGAFish and create a time-lined Implementation and Migration Plan.




    1



    0
  2. extremania says:

    D: … You recommend that lessons learned be accepted by the Architecture Board as changes to the architecture “WITHOUT” review.

    Obviously not the best answer.




    0



    0
  3. p says:

    I would say the correct answer is A.

    Phase E is completed, this is due to the following deliverables:
    a) The Implementation and Migration Plan v.0.l (draft of the plan)
    b) the Transition Architectures v1.0,
    c) the Capability Assessment

    In the next Phase, one need to finalize Implementation and Migration Plan, as per TOGAF 9.1 spec (page 144, Section 14.4 Steps for Phase F) are as follow:

    The steps in Phase F are as follows:
    – Confirm management framework interactions for Implementation and Migration Plan (see Section 14.4.1)
    – Assign a business value to each work package (see Section 14.4.2)
    – Estimate resource requirements, project timings, and availability/delivery vehicle (see Section 14.4.3)
    – Prioritize the migration projects through the conduct of a cost/benefit assessment and risk validation (see Section 14.4.4)
    – Confirm Architecture Roadmap and update Architecture Definition Document (see Section 14.4.5)
    – Complete the Implementation and Migration Plan (see Section 14.4.6)
    – Complete the architecture development cycle and document lessons learned (see Section 14.4.7)




    3



    0
  4. 404notfound says:

    The correct answer is C – As per the Togaf 9.1 Module 25 Phase F – Migration and Planning – Approach, “The focus is creation of the implementation and migration plan in co-operation with project and portfolio managers”




    1



    0
  5. Mamta says:

    D is right answer. Migration Plan .1 completed means project planning is drafted without review.
    so before review draft lesson learnt as well. Migration Plan 1 will be reviewed and approved deliverable from Phase E.




    0



    2
  6. Ketan says:

    A is the correct Answer
    Reason:->
    Case study says we are done with Phase E and “Business Value Assessment Technique” happens in Phase F.

    B is distractors and wrong
    C is 2nd Best answer
    D is also close to distractor but not completely




    1



    1
  7. Mohamed Elfouly says:

    Both A and C looks fine however the right answer is C . Why ?

    Because in the concern “Acme has a number of management
    frameworks in use, including business planning, portfolio/project management, and operations
    management.”

    There is an existing management framework in use and answer C address this point “You would assess how the plan impacts the other frameworks in use”




    3



    0