which phase of the ADM cycle do building blocks become implementation-specific?

In which phase of the ADM cycle do building blocks become implementation-specific?

PrepAway - Latest Free Exam Questions & Answers

A.
Phase A

B.
Phase B

C.
Phase C

D.
Phase D

E.
Phase E