which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?

In which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?

PrepAway - Latest Free Exam Questions & Answers

A.
Phase A

B.
Phase E

C.
Phase F

D.
Phase G

E.
Phase H

3 Comments on “which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?

  1. js says:

    TOGAF 9.1 book, section 14.4.1 – “This step is about coordinating the Implementation and Migration Plan with the management frameworks within the organization. There are typically four management frameworks that have to work closely together for the Implementation and Migration Plan to succeed”

    The answer is C.