The Requirements Management Phase _____________________.

Complete the sentence. The Requirements Management Phase _____________________.

PrepAway - Latest Free Exam Questions & Answers

A.
addresses and resolves requirements between ADM phases

B.
is a central process that prioritizes requirements for all ADM phases

C.
is used to dispose of resolved requirements for all ADM phases

D.
generates new requirements and passes them to all ADM phases

E.
stores requirements and manages their flow into relevant ADM phases

One Comment on “The Requirements Management Phase _____________________.

  1. js says:

    TOGAF 9.1 book, section 17.2.1 – Note also that the Requirements Management process itself does not dispose of, address, or prioritize any requirements; this is done within the relevant phase of the ADM. It is merely the process for managing requirements throughout the overall ADM.

    The correct answer is E.