Which risk diagramming technique you will use to communicate the causes of risk events to project stakeholders

You work as a project manager for BlueWell Inc. You have to communicate the causes of risk
events to the stakeholders. Which risk diagramming technique you will use to communicate the
causes of risk events to project stakeholders?

PrepAway - Latest Free Exam Questions & Answers

A.
Project network diagrams

B.
Ishikawa diagrams

C.
Process flow charts

D.
Influence diagrams

Explanation: