During qualitative risk analysis you want to define the risk urgency assessment. All of the following
are indicators of risk priority except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk rating

B.
Warning signs

C.
Cost of the project

D.
Symptoms

Explanation: