Which of the following project management plans defines the risk identification, analysis, response, and monit

Which of the following project management plans defines the risk identification, analysis,
response, and monitoring strategies?

PrepAway - Latest Free Exam Questions & Answers

A.
Communications Management Plan

B.
Resource Management Plan

C.
Risk Management Plan

D.
Stakeholder management strategy

Explanation: