PrepAway - Latest Free Exam Questions & Answers

Which of the following techniques is NOT used as a tool in qualitative risk analysis process?

You work as a project manager for TechSoft Inc. You are working with the project stakeholders on
the qualitative risk analysis process in your project. You have used all the tools to the qualitative
risk analysis process in your project. Which of the following techniques is NOT used as a tool in
qualitative risk analysis process?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk Data Quality Assessment

B.
Risk Categorization

C.
Risk Reassessment

D.
Risk Urgency Assessment

Explanation: