Which of the following processes involves choosing the alternative strategies, executing a contingency or fall

Which of the following processes involves choosing the alternative strategies, executing a
contingency or fallback plan, taking corrective action, and modifying the project management
plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Scope Change control

B.
Monitor and Control risk

C.
Integrated Change control

D.
Configuration Management

Explanation: