PrepAway - Latest Free Exam Questions & Answers

What approach can Amy take to create a bias against risks that will affect the schedule of the project?

Amy is the project manager for her company. In her current project the organization has a very low
tolerance for risk events that will affect the project schedule. Management has asked Amy to
consider the affect of all the risks on the project schedule. What approach can Amy take to create
a bias against risks that will affect the schedule of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
She can filter all risks based on their affect on schedule versus other project objectives.

B.
She can have the project team pad their time estimates to alleviate delays in the project
schedule

C.
She can shift risk-laden activities that affect the project schedule from the critical path as much
a possible.

D.
She can create an overall project rating scheme to reflect the bias towards risks that affect the
project schedule.

Explanation: