PrepAway - Latest Free Exam Questions & Answers

Which project management plan will be the best guide for John to communicate to the external stakeholders?

John is the project manager of the NHQ Project for his company. His project has 75 stakeholders,
some of which are external to the organization. John needs to make certain that he communicates
about risk in the most appropriate method for the external stakeholders. Which project
management plan will be the best guide for John to communicate to the external stakeholders?

PrepAway - Latest Free Exam Questions & Answers

A.
Communications Management Plan

B.
Risk Response Plan

C.
Project Management Plan

D.
Risk Management Plan

Explanation:


Leave a Reply