PrepAway - Latest Free Exam Questions & Answers

What type of risk response is being audited in this scenario?

You are the project manager of the NHQ project for your company. You are working with your
project team to complete a risk audit. A recent issue that your project team responded to, and
management approved, was to increase the project schedule because there was risk surrounding
the installation time of a new material. Your logic was that with the expanded schedule there would
be time to complete the installation without affecting downstream project activities. What type of
risk response is being audited in this scenario?

PrepAway - Latest Free Exam Questions & Answers

A.
Avoidance

B.
Mitigation

C.
Parkinson’s Law

D.
Lag Time

Explanation:


Leave a Reply