PrepAway - Latest Free Exam Questions & Answers

what step is required?

Click the Exhibit button You manage the network in the exhibit. Your customer contacts you
and requests that OSPF traffic being routed between CE-2 and CE-3 use the VPN
connection instead of the direct connection in its local network. In addition to creating a
sham link between PE-2 and PE-3, what step is required?

PrepAway - Latest Free Exam Questions & Answers

A.
Set the sham link remote metric to be lower than 8.

B.
Set the sham link local metric to be lower than 8.

C.
Set the sham link preference to be lower than 8.

D.
Set the sham link interface metric to be lower than 8.