which of the following is the best answer?

Scenario: Vittronics Ltd.
Please read this scenario prior to answering the question
Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine HeadachePain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a
precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the
onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to
be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and
safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in
the target markets.
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to
create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product
development laboratories worldwide to share information about their independent clinical trials.
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several
years. They have recently upgraded to TOGAF 9. The Vittronics Architecture Development Method (VADM) is
strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support
current good manufacturing practices and good laboratory practices in their target markets.
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture
phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of
the information that is managed in SPICE, special care was taken to ensure that each architecture domain
included an examination of the security and privacy issues that are relevant for each domain. A corresponding
SPICE Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity.
Refer to the Vittronics Ltd Scenario:
You are serving as the Lead Architect for the SPICE project team.
As required by TOGAF, the SPICE project team res completed a Business Transformation Readiness
Assessment in Phase A (Architecture Vision). In that assessment, it was determined that there are risks
associated with the adoption of the Immersive Collaborative Environment. Despite a clear expression of the
vision and the business need for utilizing SPICE to accelerate the clinical trials, the researchers have been
resisting the change because of concerns about safeguarding individually identifiable information about the
subjects who were participating in the trials.
You have been asked to recommend how this situation be managed in the implementation planning phases.
Based on TOGAF 9, which of the following is the best answer?

PrepAway - Latest Free Exam Questions & Answers

A.
You decide that in Phase E, the team creates an overall solutions strategy that can guide the Target
Architecture implementation and structure the Transition Architectures. You check that there is consensus
before proceeding.

B.
You decide to return to Phase A, where the team should brainstorm a technical solution that mitigates the
residual risks presented by the privacy issue. Then, during Phase D, you will direct the team to develop an
Architecture Building Block to manage the security risks. After that, the team should select Solution Building
Blocks that mitigate all of the identified risks and revise the Requirements Impact Statement to reflect the
changes to the high-level solutions strategy and migration plan.

C.
You decide that in Phase E, the team review the Business Transformation Readiness Assessment and
identify, classify, and mitigate the risks associated with the identified readiness factors. If the risks can be
satisfactorily mitigated, then you would continue to define a high-level solutions strategy that includes the
Transition Architectures needed to make the change culturally and technically feasible.

D.
You decide that in Phase E, the team determines an approach to implementing an overall strategic direction
that will address and mitigate the risks identified.