SureFlight Air Carrier has received approval for the acquisition of a regional carrier.
To integrate the new acquisition, a TOGAF based enterprise architecture program has been initiated. The CIO
sponsors the activity supported by the Chief Architect.
In Phase A within the initial iteration the CIO wants to ensure that the architecture activities are recognized
among the various stakeholders of the enterprise.
Refer to the scenario above
You are a consultant supporting the Chief Architect that should explain how to identify and engage the
stakeholders at this stage of the program.
Identify the best answer accordingly to the TOGAF 9 guidelines.
Choose one of the following answers

PrepAway - Latest Free Exam Questions & Answers

A.
Using the business scenarios technique you would identify supporting and not supporting stakeholders.
Then you would list the set of viewpoints that are addressing the stakeholder concerns and share these with
them.

B.
You first priority is to communicate with the regional carrier stakeholders developing a Communications
Plan to share main features and discuss opportunities with them.

C.
You conduct a pilot proof of concept during Phase A to demonstrate the technical feasibility to the
stakeholders explaining the approach available from your preferred suppliers.

D.
You identify all the main stakeholders on both the acquired carrier and the rest of the enterprise. Using a
stakeholder map, you classify and record their power in relation to this activity. You then focus on
implementing the relevant viewpoints that can address the concerns of every main stakeholder identified in
the stakeholders map.