Which four actions should you perform in sequence?

DRAG DROP
An organization has a single Exchange 2016 server. The organization plans to migrate to Exchange Online.
You have the following requirements:
– You must perform a test migration to Exchange Online with a subset of the mailboxes.
– These mailboxes must be migrated back on-premises if the test fails.
– Users must sign in to Office 365 by using the same password that they use for on-premises services.
– You must use the fewest additional servers possible to complete the migration.
You need to complete the test migration.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of
actions to the answer area and arrange them in the correct order.
Select and Place:

PrepAway - Latest Free Exam Questions & Answers

Answer:

2 Comments on “Which four actions should you perform in sequence?

  1. SureShot99 says:

    Correct.

    * Installing ADFS is pointless in this environment
    * AADC doesn’t need to be on a new server
    * Staged migration can’t be migrated back that easily.