PrepAway - Latest Free Exam Questions & Answers

which statement about the Configuration Management Stra…

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document
control process to manage all documentation requirements. The document control process was
created by the MFH Quality Manager, who now maintains all of MFH’s documents and performs an
organization-wide configuration management role. The MFH Quality Manager will administer the
configuration management procedure for the Restructuring project since this must comply with the
MFH document control process.
According to PRINCE2, which statement about the Configuration Management Strategy for the Outsourcing
project is correct?

PrepAway - Latest Free Exam Questions & Answers

A.
Every project needs a Configuration Management Strategy, even if the organization has existing
configuration management standards, because every project has different circumstances.

B.
A separate Configuration Management Strategy will be required for each of the suppliers within this project
because each will have a different way of managing and storing products.

C.
A Configuration Management Strategy is unnecessary for this project because the MFH document control
process is documented. It is acceptable simply to reference this in the Quality Management Strategy.


Leave a Reply