PrepAway - Latest Free Exam Questions & Answers

Which 2 statements apply to the Budgets section?

Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about
current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to
allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to
continue, they will give the approval to launch the internal label design competition. Competition rules will be
required to communicate details of the competition to the staff. The chosen label design will then be selected
from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing
department. The selected photos will be chosen from these. Monthly calendar displays will be created to show
the required layout of each page.
Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this
question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are
being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago
the professional photographer produced the photo session schedule based on the operational staff schedule.
The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Budgets section?

PrepAway - Latest Free Exam Questions & Answers

A.
Amend entry 15 because it should also include the cost of management activities.

B.
Delete entry 16 because timescales should NOT be shown under the heading of budgets.

C.
Delete entry 17 because the risk budget should be shown in the Risk Management Strategy.

D.
Add ‘Change budget – £500’.

E.
Add ‘Cost tolerance – +£6k 1-£6k