How should the Project Manager record this observation …

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the
increased marketing activities of its competitors. To help counter this, the company has decided to create a
promotional calendar for next year for all its current and prospective customers. The end product of this project
will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out
previously, and must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each page of the
promotional calendar. The prepared calendar pack will consist of:
Design for each month – correctly showing at public holidays and new company logo
Selected photographs- 12 professionally-produced photographs, showing different members of staff
Selected paper and selected envelope – for printing and mailing the calendar
Chosen label design – a competition to design a label will be held as part of this projectList of customers – names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing departments
Confirm compliance with the Data Protection Legislation
Create a design for each month – this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of
the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is
not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine
whether tie project should continue. It is now 05 October and the prepared calendar pack must be delivered to
the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas.
The cost of the activities to develop the specialist products and the cost of the project management activities
are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost
tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
Whilst identifying the mailing costs for the calendars the Project Manager was surprised to find the costs could
vary considerably depending on the size of the package and the delivery service used. For the purpose of this
project, the Project Manager has selected an appropriate service but feels that a corporate standard for
postage would have reduced the time and effort invested. It could reduce the company’s overheads by up to
£20k per year. How should the Project Manager record this observation within the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Produce a project mandate, outlining the potential savings to be achieved by the introduction of a corporate
standard.

B.
Make a note of the observation in the Daily Log to be transferred to a Benefits Review Plan at the end of the
project.

C.
Record the observation in an Exception Report to the Project Board.

D.
Make an entry in the Lessons Log for future consideration by corporate management.